Skip to content
HotspoteasyQuestion #9

As a result of updated external regulations a project manager has been asked to upgrade the operation system for a call center. The project manager is beginning to meet with and segment the stakeholders involved. How should the project manager categorize the call center staff? Click on the correct section of the power/interest grid.

Click the correct area in the image.