Single choiceeasyQuestion #4A research and development team is finishing up a two-year initiative. The project manager is focused on the closing activities for the project. Which activity should be considered as a priority?A.Mark the product backlog completion status and update the communications management plan.B.Ensure that knowledge transfer activities are executed as plannedC.Release the resources and plan for a project completion celebration.D.Hold a steering committee meeting to inform them of the project completionSubmit