A hospital is running a project for one of their internal critical systems to manage billing, patient data, and record management along with consultation reports and input from physicians. The project manager now needs to categorize the identified risks. Drag each risk type on the left to its correct example on the right.
Match every item with the correct option.
Fixed itemDrag these options into the correct order
1. Technical risk
The interfaces to medical devices require support from vendors.
2. Commercial risk
Availability of resources for the documentation and user manual preparation needs as this was not originally planned to be taken up by the project team.
3. Management risk
Needs regulatory compliance and clearance standards for incorporation into the system
4. External risk
Availability of the output formats of the files to interface with the data and record management systems on time as they are not available with the project manager.